Design Engine | Oxford Brookes University John Henry Brookes and Abercrombie Building

Architecture 0722_N602

Purpose

In the context of historic piecemeal development, the need to address the campus as a whole was recognised. This was then enabled by the production of a masterplan in 2007. Originating as a standalone student centre, the concept was developed to more fundamentally and visibly connect the existing campus, and in doing so provide a suite of internal and external spaces of the highest quality, as befits the University’s academic status.

0722_N598

Approach

The design approach was closely allied to this ambition, and one of environmental performance. Close coordination between environmental engineer and architect was undertaken from the outset to develop and test iterations of the design in a virtual environment. The integration of structure, services and architectural elements brought similarly close, collaborative working amongst the design team.

0722_N604

0722_N605Construction method

The building is principally of a hybrid insitu and precast concrete construction. Structural materials, in particular concrete, are integral to the appearance and environmental performance of the building. These are placed alongside and in contrast with other, largely self-finished materials.

0722_N607The exposed concrete provides thermal mass, which tempers heating and cooling loads in parallel with natural ventilation. Concrete’s robustness is appropriate, and its use allows partitions to be demountable, providing a flexibility of accommodation in anticipation of changing teaching patterns. Precast elements are largely used where benefit can be gained from repetition. In situ elements include geometrically and structurally more complex components.

0722_N610Procurement

The project was subject of a two stage tender, with a ‘mini package’ process to select the final contractor from a shortlist of 2. Tender packages were reviewed in an open book forum for transparency and best value. Early contractor involvement enabled by the two-stage tender facilitated familiarisation with a large and complex construction project, development of construction methodologies and the bespoke facade systems. The project was undertaken under an NEC3 traditional contract.

0722_N597Design & construction quality, management

Ambition for architectural quality derived from the brief. Rigorous review was undertaken, including by the South East Regional Design Panel as part of the Planning process. Functional quality was addressed similarly, a consultation and briefing process included meeting with the University’s Environmental Group. Close coordination among a design team incorporating specialist consultants addressed these ambitions.

0722_N586Off-site manufacturing was used where appropriate. A unitised facade system allowed dimensional accuracy, environmental performance, and speed of construction.

0722_N589Full size mock-ups of concrete frame and facade elements allowed quality to be assessed and improved prior to fabrication. A full time on-site consultant team, the main contractor and specialist subcontractors worked closely to develop and coordinate subcontractor design. In conjunction with the NEC3 contract this organisation allowed timely identification and resolution of issues.

0722_N594Value, Response

The project is of a scale not previously undertaken by the University. As such, it was subject to a process of tight cost control. Ultimate value perhaps derives from the realisation of an intervention on such a scale, in one step. As such, benefit to the experience of students, staff and public alike is greater than separate smaller buildings.

0722_N595Since the opening of its new Abercrombie building in 2012, the School of Architecture has enjoyed an appreciable rise in applications to its courses, one indicator of the project’s success. Indications since the opening of the John Henry Brookes Building in March 2014 are of a student body at home in their new building from the outset, and of University staff responding with great enthusiasm.

0722_N608‘…the beginning of a great modern cathedral of learning’ Shami Chakrabarti, Oxford Brookes Chancellor, speaking at the opening of the new Abercrombie building

0722_N593

Location: Oxford Brookes University, Headington Campus, Gipsy Lane, Oxford, UK
Architects: Design Engine
Project Name: Oxford Brookes University John Henry Brookes and Abercrombie Building
Company marketing contact: Phil Webb
Photography: Nick Kane
Date Completed: 31/01/2014
Date Project came into use: 24/02/2014
Cost of project on completion: £83,020,000
Structural and Civil Engineers: Ramboll UK
Environmental Services, Fire Consulants: Grontmij
Landscape Architect: Land Use Consultants
Specialist Lighting Consultant: Speirs & Major
Catering Consultant: Tricon Foodservice Consultants
Signage Consultant: Holmes Wood
Acoustic Consultant: Sandy Brown Associates
Access Consultant: QMP
Facade Access Consultants: Reef
Project Manager and Cost Consultant: Turner & Townsend
 
 
Sharing is Caring...
Share on FacebookTweet about this on TwitterShare on Google+Share on RedditPin on PinterestShare on LinkedInShare on StumbleUponShare on Tumblr

 
Sharing is Caring...
Share on FacebookTweet about this on TwitterShare on Google+Share on RedditPin on PinterestShare on LinkedInShare on StumbleUponShare on Tumblr

Have anything to say?

// arthitectural / You may also like to see...

The new campus of TAC SEV is built across from the existing property of Tarsus American College (TAC). Considering its proximity to the historic context of the school, the new campus is conceived, as a design principle, a part of the TAC campus it is separated from by a road that traverses the premises. An […]


more